Projects

April 7, 2023

BMA Installs 10,000 Feet Pipe between CR 5719 and CR 679

10,000 feet of 48″ pipe has been installed off of the A4 Main Canal between CR 5719 to CR 679. This newly installed pipe will improve delivery time and conservation. […]
October 15, 2020

Proposed 2021 Piping Projects

September 21, 2018

D1 to Collazo Piping 2018

September 19, 2018

2019 Piping Projects

September 19, 2018

2018 Piping Phase 2

March 22, 2018

2018 Piping Projects

2018 Piping Projects
April 13, 2017

Fort Ewell Siphon

The piping of 1,900 feet on the Fort Ewell Siphon has been completed. PVC pipe was installed to replace the pre-existing concrete pipe which had numerous leaks. The piping project […]
January 26, 2017

Hunter’s Lake Piping Project

The piping of over 18,000 feet on the D-1 canal at Hunter’s Lake has been completed and will eliminate an ongoing leakage and maintenance problem for BMA. The piping project was completed in January 2017 at a cost of $158,636.16. BMA is continuing efforts to improve the efficiency of water delivery to the Land Owners and eliminate the loss of valuable water.