2018 Piping Phase 2

2018 Piping Phase 2

The phase 2 of piping for 2018 was approved by board action on July 9, 2018 at the Regular Scheduled Board Meeting. These projects are ongoing and will be completed by the end of 2018.

ItemPipe | DistanceMaterial Est. CostEst. TimeDate
Item1# 1 Southwest of Pearson CR 4514

# 1 Southwest of Pearson CR 4514

12” Pipe 2,325 Feet$16,275.004 weeksJuly 9, 2018 – Aug. 15, 2018
Item2# 2 A5 Pearson to CR 471

# 2 A5 Pearson to CR 471

12” Pipe 4,255 Feet$29,785.004 weeksAug. 15, 2018-Sept. 15, 2018
Stagging dirt as of 7/3/2018 waiting for cotton to finish watering.
Item3# 3 D2 to CR 6611

# 3 D2 to CR 6611

18” Pipe 2,175 Feet$28,818.752 weeksSept. 15, 2018 – Sept. 30, 2018
Item4# 4 D2-V1 on CR 6611 to Hwy 132

# 4 D2-V1 on CR 6611 to Hwy 132

18” Pipe 2,595 Feet$34,383.754 weeksOct. 1, 2018 – Oct. 31, 2018
Item5# 5 HWY 132 to Saenz CR 6721

# 5 HWY 132 to Saenz CR 6721

12” Pipe 3,515 Feet$24,605.004 weeksNov. 1, 2018 – Nov. 28, 2018
Item6# 6 Weimer to CR 664

# 6 Weimer to CR 664

48” Pipe 1,200 Feet$71,700.004 weeksDec. 1, 2018 – Dec. 31, 2018
**Item #6 is optional, if timming and budget allow.
If not, will be included in 2019 budget.
Total: 16,065 feet pipedTotal: $205,567.50