April 7, 2023
10,000 feet of 36″ pipe has been installed off of the A4 Main Canal between CR 5719 to CR 679. This newly installed pipe will improve delivery time and conservation. […]
October 15, 2020
October 15, 2020
Categories
September 21, 2018
September 21, 2018
Categories
September 19, 2018
September 19, 2018
Categories
September 19, 2018
September 19, 2018
Categories
March 22, 2018
April 13, 2017
April 13, 2017
Categories
The piping of 1,900 feet on the Fort Ewell Siphon has been completed. PVC pipe was installed to replace the pre-existing concrete pipe which had numerous leaks. The piping project […]
January 26, 2017
January 26, 2017
Categories
The piping of over 18,000 feet on the D-1 canal at Hunter’s Lake has been completed and will eliminate an ongoing leakage and maintenance problem for BMA. The piping project was completed in January 2017 at a cost of $158,636.16. BMA is continuing efforts to improve the efficiency of water delivery to the Land Owners and eliminate the loss of valuable water.