10,000 feet of 36″ pipe has been installed off of the A4 Main Canal between CR 5719 to CR 679. This newly installed pipe will improve delivery time and conservation. […]
The piping of 1,900 feet on the Fort Ewell Siphon has been completed. PVC pipe was installed to replace the pre-existing concrete pipe which had numerous leaks. The piping project […]
The piping of over 18,000 feet on the D-1 canal at Hunter’s Lake has been completed and will eliminate an ongoing leakage and maintenance problem for BMA. The piping project was completed in January 2017 at a cost of $158,636.16. BMA is continuing efforts to improve the efficiency of water delivery to the Land Owners and eliminate the loss of valuable water.