2018 Piping Phase 2
The phase 2 of piping for 2018 was approved by board action on July 9, 2018 at the Regular Scheduled Board Meeting. These projects are ongoing and will be completed by the end of 2018.
Item | Pipe | Distance | Material Est. Cost | Est. Time | Date |
# 1 Southwest of Pearson CR 4514# 1 Southwest of Pearson CR 4514 | 12” Pipe 2,325 Feet | $16,275.00 | 4 weeks | July 9, 2018 – Aug. 15, 2018 |
# 2 A5 Pearson to CR 471# 2 A5 Pearson to CR 471 | 12” Pipe 4,255 Feet | $29,785.00 | 4 weeks | Aug. 15, 2018-Sept. 15, 2018 Stagging dirt as of 7/3/2018 waiting for cotton to finish watering. |
# 3 D2 to CR 6611# 3 D2 to CR 6611 | 18” Pipe 2,175 Feet | $28,818.75 | 2 weeks | Sept. 15, 2018 – Sept. 30, 2018 |
# 4 D2-V1 on CR 6611 to Hwy 132# 4 D2-V1 on CR 6611 to Hwy 132 | 18” Pipe 2,595 Feet | $34,383.75 | 4 weeks | Oct. 1, 2018 – Oct. 31, 2018 |
# 5 HWY 132 to Saenz CR 6721# 5 HWY 132 to Saenz CR 6721 | 12” Pipe 3,515 Feet | $24,605.00 | 4 weeks | Nov. 1, 2018 – Nov. 28, 2018 |
# 6 Weimer to CR 664# 6 Weimer to CR 664 | 48” Pipe 1,200 Feet | $71,700.00 | 4 weeks | Dec. 1, 2018 – Dec. 31, 2018 |
**Item #6 is optional, if timming and budget allow. If not, will be included in 2019 budget. | Total: 16,065 feet piped | Total: $205,567.50 |