2019 Piping Projects

2019 Piping Projects

The piping schedule for 2019 was approved by board action on September 10, 2018 at the Regular Scheduled Board Meeting. These projects will begin in January 2019.

ItemTotal FeetTotal CostEst. Dates
Item1-19Main Canal from cement through to inlet of Siphon #1

Main Canal from cement through to inlet of Siphon #1

Twin 48" Hancor plastic pipe at $114.00

2,600 feet$306,500.001/2/2019 - 1/31/2019
Item2-19Kirby Lake to Wheeler Road

Kirby Lake to Wheeler Road

1240 feet 18 inch at $13.50 - $16,740.00
2 boxes, 2 headwalls, 3 screw gates - $3,500.00

$20,240.002/1/2019 - 3/1/2019
Item3-19High Section past Shrimp Farm to Youngman Place

High Section past Shrimp Farm to Youngman Place

5000 feet of 18" - $67,500.00
2300 feet of 12" - $17,250.00
4 boxes, 4 gates - $6,000.00

7,300 feet$90,750.003/2/2019 - 4/30/2019
Item4-19Main D-1 to Duncan Place

Main D-1 to Duncan Place

7000 feet 18" - $94,500.00
5120 feet 12" - $38,400.00
11 boxes, 25 screw gates - $23,700.00

12,115 feet$156,600.005/1/2019 - 8/31/2019
$574,090.00