2019 Piping Projects
The piping schedule for 2019 was approved by board action on September 10, 2018 at the Regular Scheduled Board Meeting. These projects will begin in January 2019.
| Item | Total Feet | Total Cost | Est. Dates |
Main Canal from cement through to inlet of Siphon #1Main Canal from cement through to inlet of Siphon #1Twin 48" Hancor plastic pipe at $114.00 | 2,600 feet | $306,500.00 | 1/2/2019 - 1/31/2019 |
Kirby Lake to Wheeler RoadKirby Lake to Wheeler Road1240 feet 18 inch at $13.50 - $16,740.00 | $20,240.00 | 2/1/2019 - 3/1/2019 | |
High Section past Shrimp Farm to Youngman PlaceHigh Section past Shrimp Farm to Youngman Place5000 feet of 18" - $67,500.00 | 7,300 feet | $90,750.00 | 3/2/2019 - 4/30/2019 |
Main D-1 to Duncan PlaceMain D-1 to Duncan Place7000 feet 18" - $94,500.00 | 12,115 feet | $156,600.00 | 5/1/2019 - 8/31/2019 |
| $574,090.00 |

Main Canal from cement through to inlet of Siphon #1
Kirby Lake to Wheeler Road
High Section past Shrimp Farm to Youngman Place
Main D-1 to Duncan Place