2018 Piping Projects
PUBLIC NOTICE
2018 Piping Projects
Item # 1 Main to Sobeczek 24” Pipe 1,325 Feet Material Est Cost 27,125.00
Estimated Time: 2 Weeks Date: February 1 – February 14, 2018
Item # 2 Sobeczek to Fischer 18” Pipe 3,204 Feet Material Est Cost 43,675.00
Estimated Time: 5 Weeks Date: February 15 – March 22, 2018
Item # 3 Fischer to Sylvan Mangold 12” Pipe 601 Feet Material Est Cost 4,350.00
Estimated Time: 2 Days Date: March 26 – March 28, 2018
Item # 4 Miles to Sherwood 18” Pipe 2,596 Feet Material Est Cost 37,025.00
Estimated Time: 3 Weeks Date: March 29 – April 19, 2018
Item # 5 (a) Montgomery to 463 18” Pipe 4,539 Feet Material Est Cost 63,945.00
Estimated Time: 3 Weeks Date: April 20, – May 11, 2018
Item # 7 (a) FM 463 to CR 6712 18” Pipe 1,908 Feet Material Est Cost 25,131.00
Estimated Time: 2 Weeks Date: May 14 – May 28, 2018
Item # 5 (b) Montgomery to 463 18” Pipe 4,539 Feet Material Est Cost 63,945.00
Estimated Time: 3 Weeks Date: May 29, – June 19, 2018
Item # 7 (b) FM 463 to CR 6712 18” Pipe1,908 Feet Material Est Cost 25,131.00
Estimated Time: 2 Weeks Date: June 20 – July 4, 2018
Item # 5 (c) Montgomery to 463 18” Pipe 4,539 Feet Material Est Cost 63,945.00
Estimated Time: 2 Weeks Date: July 5, – July 19, 2018
Item # 8 FM 463 to Elkins 18” Pipe 1,221 Feet Material Est Cost 17,305.00
Estimated Time: 2 Weeks Date: July 20 – August 3, 2018
Item # 5 (d) Montgomery to 463 18” Pipe4,539 Feet Material Est Cost 63,945.00
Estimated Time: 2 Weeks Date: August 6, – August 20, 2018
Item # 6 FM 463 to Colazos 12” Pipe2,501 Feet Material Est Cost 21,500.00
Estimated Time: 4 Weeks Date: August 21 – September 11, 2018
Item # 9 Main Shot Creek 2,417 Feet Material Est Cost 121,000.00
Estimated Time: 6 Weeks Date: November 15 – Dec. 31, 2018
Estimated material cost of all projects $ 361, 056.00