2018 Piping Projects

2018 Piping Projects

PUBLIC NOTICE

 

2018 Piping Projects

 

Item # 1                Main to Sobeczek                24” Pipe                1,325 Feet            Material Est Cost 27,125.00

Estimated Time:   2 Weeks                                Date:  February 1 – February 14, 2018

 

Item # 2                Sobeczek to Fischer            18” Pipe                3,204 Feet            Material Est Cost 43,675.00

Estimated Time:   5 Weeks                                Date:   February 15 – March 22, 2018

 

Item # 3                Fischer   to Sylvan Mangold   12” Pipe   601 Feet        Material Est Cost 4,350.00

Estimated Time:   2 Days                                    Date:   March 26 – March 28, 2018

 

Item # 4                Miles to Sherwood             18” Pipe                2,596 Feet            Material Est Cost 37,025.00

Estimated Time:   3 Weeks                                Date:  March 29 – April 19, 2018

 

Item # 5 (a)           Montgomery to 463    18” Pipe 4,539 Feet  Material Est Cost 63,945.00

Estimated Time:   3 Weeks                                Date:  April 20, – May 11, 2018

 

Item # 7 (a)           FM 463 to CR 6712   18” Pipe  1,908 Feet    Material Est Cost 25,131.00

Estimated Time:   2 Weeks                                Date:  May 14 – May 28, 2018

 

Item # 5 (b)          Montgomery to 463    18” Pipe 4,539 Feet  Material Est Cost 63,945.00

Estimated Time:   3 Weeks                                Date:  May 29, – June 19, 2018

 

Item # 7 (b)          FM 463 to CR 6712 18” Pipe1,908 Feet        Material Est Cost 25,131.00

Estimated Time:   2 Weeks                                Date:  June 20 – July 4, 2018

 

Item # 5 (c)           Montgomery to 463 18” Pipe 4,539 Feet     Material Est Cost 63,945.00

Estimated Time:   2 Weeks                                Date:  July 5, – July 19, 2018

 

Item # 8                               FM 463 to Elkins  18” Pipe                1,221 Feet            Material Est Cost 17,305.00

Estimated Time:   2 Weeks                                Date:  July 20 – August 3, 2018

 

Item # 5 (d)          Montgomery to 463    18” Pipe4,539 Feet   Material Est Cost 63,945.00

Estimated Time:   2 Weeks                                Date:  August 6, – August  20, 2018

 

Item # 6                                FM 463 to Colazos  12” Pipe2,501 Feet         Material Est Cost 21,500.00

Estimated Time:   4 Weeks                                Date:  August 21 – September 11, 2018

 

Item # 9                               Main Shot Creek     2,417 Feet                         Material Est Cost 121,000.00

Estimated Time:   6 Weeks                                Date:  November 15 – Dec. 31,  2018

 

Estimated material cost of all projects  $ 361, 056.00